The time taken to build a housing unit is calculated after evaluating each stage of the design separately:
- Engineering design 4-6 weeks if the design is provided by the client. If the client choses a design done by SHB, the design stage will take about 1 week.
- Manufacturing 3-4 days.
- Installation and finishing 2-4 weeks.